Pine Creek Bridge
C.L. Heilman replaced an old three-span bridge in Pinehurst, Idaho with a new single-span concrete bridge. A temporary bridge was used to keep the road open and divert a water main during construction. The project also featured driven H-Pile, 12" HPDE fusion welding, casing welding, road construction and decorative soldier pile retaining wall. The project was completed successfully within 4 months through partnership with HMH Engineering, CDA Crane and Shoshone County.